Updates

Check here for updates about me, my projects and other fun stuff!

  • Project Complete!!!

    After 8 long months, the construction phase of the project was finally completed on May 20th at 1pm. The entire project took 20 volunteers, 256-288ga of water, 336ft…

    Continue Reading

    4 min read

  • Pouring Holes 3, 4, and 8

    Pouring Holes 3, 4, and 8

    Before pouring holes 3 and 4, we had to create and use wooden stakes to keep the frames in place. Afterwords, we divided the work up so that…

    Continue Reading

    4 min read

  • Pouring Hole #6

    Pouring Hole #6

    After waiting some time, we were ready to begin pouring concrete on Hole #6. It took a total of 18 bags of 80lb concrete and about a couple…

    Continue Reading

    4 min read

  • Framing Holes 3, 4, 6 & 8

    Framing Holes 3, 4, 6 & 8

    Due to the cold weather, the project was put on hold until the temperature increased consistently to a point where we could continue setting concrete/framing. Now we’re back…

    Continue Reading

    4 min read

  • Concrete time for 2 & 7

    Concrete time for 2 & 7

    Today we were ready to concrete pads 2 & 7. We started with pad number 2. We added the weed barrier and the chicken wire on top of…

    Continue Reading

    4 min read

  • Moving on to pad 2

    Moving on to pad 2

    Similar to pad 7, pad 2 was another one that needed a retaining wall to prevent dirt from covering the hole. After clearing and leveling the area, we…

    Continue Reading

    4 min read